A new power plant was built at the busiest airport in the AENA network. It is designed to replace three existing substations and ensure both normal and emergency power supply to Terminals 1, 2, and 3, as well as future expansions.
The plant centralises part of the airport’s existing power distribution. It has three 45 kV incoming power supplies and steps the voltage down to 15 kV to feed the distribution lines—comprising 300,000 metres of cable—to a total of 20 transformer centres. The installation includes three 15/20 MVA power transformers and approximately 189 medium-voltage switchgear cubicles.
For emergency power supply, the plant includes four 4 MVA generator sets, with provision for two additional sets of the same capacity in the future. The generator sets produce electricity at 6 kV, so each is paired with a step-up transformer to raise the voltage to 15 kV.