3.1 MW Behind-the-Meter Biogas Combined Heat and Power Plant for Bacardí in Puerto Rico
sector:
Energy
Date:
2022
Location:
Cataño, Puerto Rico
Services:
EPC — Engineering, Procurement & Construction / Operation and Maintenance / Energy / PPA / Energy as a Service
Electricity, steam, and cooling from distillery by-products
Bacardí’s Behind-the-Meter trigeneration plant in Cataño, Puerto Rico, was commissioned in 2022, with a capacity of 3.1 MW of electricity, 34 t/h of total steam, and 300 RT of cooling. The project is based on a circular-economy model that converts by-products from rum production into biogas to generate useful energy for the distillery.
The installation includes a biogas-fired gas turbine that can also run on propane. The turbine generates electricity for industrial processes, while its heat is recovered to produce steam. SAMPOL’s scope included the design, investment, full EPC delivery, and operations and maintenance (O&M) under a PPA / Energy-as-a-Service (EaaS) contract.
On-site generation with the public grid as backup
The plant normally operates in parallel with the public grid, which primarily provides backup and additional supply security rather than meeting peak demand.
Recovering energy from distillery by-products and capturing heat from the turbine helps reduce fossil fuel consumption and improve operational efficiency through the integrated production of electricity, steam, and cooling.